Your lawyers since 1722

Building/Project Details

Building/Project NameConstruction Industry Council - Zero Carbon Park Construction / refurbishment date26/06/2012 Building/Project Size3,300 sqm
Building/Project Typeother Address 8 Sheung Yuet Road, Kowloon Bay, Kowloon East, Hong Kong China Region asia pacific

Performance Details

Net Zero Operational Carbon

Buildings or developments that are verified and certified as “net zero operational energy and/or carbon.” The building should demonstrate the highest levels of energy efficiency with the use of either renewables generated onsite or renewable energy procured offsite.

Achieved Certification Scheme: GBCSA Net Zero / Net Positive Carbon
Achieved Certification Level: BEAM Plus Platinum Offsite Renewable Energy Procurement Source: Biodiesel Verification Year: 2015

Tell us your story

CIC-Zero Carbon Park (CIC-ZCP), the first zero carbon building designed to be energy-positive from a life-cycle perspective in the tropics, is a milestone for Hong Kong, in terms of its visions, design innovations, execution and implementation from the integrated design process to the continual optimisation of the building performances in the operational phase since its opening in 2012. Energy hierarchy with its priority on energy demand control is adopted. Passive design with climate-responsive built form, orientation, layout and envelope enhance natural ventilation, daylighting and solar shading. The spacious entrance hallway is orientated and fully opened to the prevailing summer breeze, and provides a comfortable setting for gathering and temporary exhibition without the use of air-conditioning. An ultra-low OTTV of 11 W/m2 is achieved mainly due to optimized window-to-wall ratio, deep overhang over the south facade, external shading fins, minimized east and west facades / windows, high performance glazing system, and shaded and insulated roof. These passive design measures are expected to reduce energy consumption by 20% as compared to the current building industry benchmark. The use of highly energy-efficient active systems like high-volume-low-speed fans, high temperature cooling system, coupling with smart control can further reduce the potential energy demand by 25%. CIC-ZCP targets “Energy Plus” which goes beyond conventional scope of carbon neutrality by producing more energy than its own needs over an annual basis, to offset the embodied carbon of its construction process and major structural materials. On-site renewable energy generation by biodiesel tri-generation and state-of-the-art photovoltaic (PV) technologies have been adopted.

Eco-efficiency is the key design concept which targets for high environmental quality and minimized loading. Green, clean and lean design and construction approach with an emphasis on resource conservation for less material and less waste (e.g. fair-faced concrete, unpainted metal works) has been adopted. Balanced cut and fill for site formation introduces sheltered plaza and green terraces with surrounding formed berms and trees. The construction debris from demolition works were used as infill for the gabion planter walls around the berms, and no environmental loading of exporting the waste was resulted. Regionally manufactured eco-pavers would absorb air pollutants by their titanium oxide coating and did not require high embodied energy for transportation of the materials. Reinforced concrete with high PFA content was used to minimize the carbon footprint of the structure. Consideration for embodied carbon of the materials and construction becomes more important in the life cycle carbon footprint assessment in particular when the operational energy demand is reduced. To evaluate and optimize CIC-ZCP’s building environmental performance and operation, a custom-developed BEPAD (Building Environmental Performance Assessment Dashboard) system is provided. The system acts as a graphical user interface (GUI) for interactive display of real-time data and track records of building environmental performances as monitored by the BMS (Building Management System) using over 2,800 sensing points in the building. Building environmental performances of the following 6 categories are displayed: energy use (EU), site aspects (SA), indoor environmental quality (IEQ), material aspects (MA), water use (WU) and occupancy data (OC). Four outdoor weather stations have been installed within the site to collect microclimatic data that will inform and optimize the performances of building services systems.

Submitter's Details

OrganisationConstruction Industry Council - Zero Carbon Park Member of GBCHKGBC

CIC-Zero Carbon Park (CIC-ZCP), the first zero carbon building designed to be energy-positive from a life-cycle perspective in the tropics, is a milestone for Hong Kong, in terms of its visions, design innovations, execution and implementation from the integrated design process to the continual optimisation of the building performances in the operational phase since its opening in 2012.